The Grenfell Tower fire fundamentally changed fire safety expectations for high-rise residential buildings in the UK. Since 2017, legislation, guidance and industry practice have placed far greater emphasis on external wall systems, the quality of fire risk assessments, and the ongoing duties of those responsible for multi-occupied residential buildings.
This guide explains the current position on external wall systems, the status of the EWS1 form, and the practical ongoing duties that apply to Responsible Persons and Accountable Persons.
Several key pieces of legislation now shape fire safety in high-rise residential buildings:
Fire Safety Act 2021
This Act clarified that, in buildings containing two or more sets of domestic premises, the Regulatory Reform (Fire Safety) Order 2005 applies to the building’s structure, external walls (including cladding, insulation, balconies and other attachments) and flat entrance doors that open onto common parts. Fire risk assessments must take these elements into account.
Building Safety Act 2022
This created a new regime for higher-risk buildings (generally those at least 18 metres in height or with at least seven storeys, containing two or more residential units). It introduced the roles of Accountable Person and Principal Accountable Person, the requirement for a safety case, and the “golden thread” of building information.
Fire Safety (England) Regulations 2022
These regulations imposed additional specific duties on Responsible Persons for multi-occupied residential buildings, with the most detailed requirements applying to high-rise buildings (18 metres or more, or seven or more storeys).
Together, these measures mean that external wall systems can no longer be treated as outside the scope of day-to-day fire safety management.
External wall systems include cladding, insulation, cavity barriers, fixings, balconies and other attachments. In many existing buildings these systems were not designed or assessed with the current understanding of fire spread risk.
Where the external wall construction is traditional masonry with no significant combustible materials, the risk of external fire spread may be low and can often be addressed with a clear statement in the fire risk assessment. Where combustible materials are present or suspected, a more detailed appraisal is usually required.
PAS 9980 provides the current methodology for conducting a Fire Risk Appraisal of External Walls (FRAEW). This is a risk-based assessment that considers the materials, the design of the wall system, the building’s height and use, and the overall fire strategy. The FRAEW feeds into the building’s fire risk assessment and helps determine what, if any, remediation or interim measures are needed.
For high-rise residential buildings, Responsible Persons must also provide the local Fire and Rescue Service with information about the design and materials of the external walls, including an assessment of the risk of fire spread and any mitigating steps taken.
The EWS1 form was introduced in 2019 as an industry response to lending and valuation difficulties caused by uncertainty over external wall fire risk. It is not a statutory document and does not replace the legal requirement for a suitable and sufficient fire risk assessment or, where needed, a FRAEW under PAS 9980.
Key points in 2026:
Building owners and managing agents should treat the EWS1 as a supporting document for property transactions, not as a substitute for their ongoing legal duties under the Fire Safety Order and related legislation.
Responsible Persons (and, where applicable, Accountable Persons) have continuing obligations that go well beyond obtaining a one-off assessment. These include:
Fire risk assessment
A suitable and sufficient assessment must cover the common parts, structure, external walls and flat entrance doors. It must be recorded in full and kept under review. Where external wall risk requires specialist input, a FRAEW should be commissioned.
Information for the Fire and Rescue Service
For high-rise residential buildings, electronic information on the external wall system, floor plans and building plans must be provided and kept up to date. A secure information box with hard-copy plans and contact details must also be maintained.
Fire door checks
In multi-occupied residential buildings over 11 metres, communal fire doors must be checked at least every three months and flat entrance doors at least annually (on a best endeavours basis).
Resident information
Clear fire safety instructions and information about the importance of fire doors must be provided to residents.
Maintenance and cooperation
Fire safety systems and measures must be maintained in efficient working order. Where more than one Responsible Person or an Accountable Person is involved, cooperation and information sharing are required.
Higher-risk buildings
Additional duties under the Building Safety Act apply, including registration, safety case reports and management of building safety risks.
At Fire Safety Risk Assessment we support landlords, freeholders and managing agents with fire risk assessments that properly address post-Grenfell requirements for high-rise and multi-occupied residential buildings. This includes consideration of external wall systems, the need for FRAEW input, and the ongoing duties under the Fire Safety Order, Fire Safety Act and Building Safety Act.
We work across Birmingham, Manchester, Warrington, the West Midlands and the wider UK.
Related reading on our site:
Fire safety in high-rise residential buildings is no longer limited to the internal common parts. External wall systems, flat entrance doors and the overall fire strategy must form part of a living, documented management process. The EWS1 form remains relevant for many property transactions, but the legal duties of the Responsible Person and Accountable Person are broader and ongoing.
If your building’s fire risk assessment does not clearly address external walls, or if you need support in understanding current FRAEW and EWS1 expectations, a professional review will provide clarity and help demonstrate compliance.
Need a Fire Risk Assessment that addresses high-rise and external wall requirements?
Contact Fire Safety Risk Assessment today for practical, up-to-date advice.